Combining Risk FactorsIn "Waltzing with Bears" Tom DeMarco and Tim Lister introduce the very useful concept of the "Uncertainty Diagram", the probability distribution for project metrics such as delivery date, expenditure or benefit delivery. This is used, for example, to assess the likelihood of delay from a given risk. However, when it comes to evaluating the net effect of several risk factors they rely entirely on Monte-Carlo simulation, claiming that the mathematics for an analytical solution are too complicated. While this might be true for complex curves, it isn't true where the curve is defined by, or can be approximated by, a few discrete points, which will be a common case in practice. Here's my attempt to show how this can be explained, and how a relatively simple analytical solution can then be used in place of simulation. Consider the following two uncertainty diagrams, which show how two separate risk factors, Factor 1 and Factor 2, will affect a project's completion date relative to the earliest possible completion date.
(For simplicity we refer to delivery after the earliest possible date as a "delay", although a good project manager will actually agree a realistic target later than the earliest possible date.) We want to combine these two profiles into a single probability function (which can then be expressed as an uncertainty diagram). Consider the first value in each distribution, the probability of delivery up to one month after the earliest possible date. If Factor 1 affects the project so that there is up to one month's delay AND Factor 2 affects the project so that there is up to one month's delay then delivery will be delayed up to 2 months. This is the smallest net delivery delay we can assess. Note the use of the word "AND". This means we simply multiply the probabilities for those two cases, giving a net probability of 0.01. Delivery delayed between two and three months means that either Factor 1 produces one month's delay AND Factor 2 produces two month's delay OR Factor 1 produces two month's delay AND Factor 2 produces one month's delay. Again, we multiply appropriate pairs of individual probabilities, then add the results together (where we use the word "OR"). The following spreadsheet shows the formulae for all the possible outcomes:
The right-most column is our net probability function, which can then be plotted as an uncertainty diagram:
In summary, as long as the two factors are independent (which is also the underlying assumption for the simulation approach) you can combine them using simple probability rules. To produce a single net uncertainty diagram they need to be in the same units, but you could produce a list, for example, showing probabilities like "the probability of two month's delay and $10,000 budget overrun". I haven't found a way of doing this using simple Excel functions, but it would be very straightforward to write a small VBA routine to dynamically build the formulas given the input columns. I may have a go at this in a future version of this paper. Click here to download the example spreadsheet.
© Questa Computing Ltd. 2003 |